Design and launch of manufacture of cut-off gate valves of plate design

Project implementation timeframe: 01/09/2011 – 31/12/2012

Coordinator: Fabryka Armatur JAFAR S.A.

Project purposes: Design and launch of manufacture of cut-off gate valves of plate design
The project consisted of 15 tests of which 4 were assigned to PIAP.

Work done by PIAP:

  • Determination of requirements and structural/technology guidelines for the design of the plate gate valves;
  • Analysis of lifetime and materials plus selection of measuring probes or inspection cameras and design of insertion of these instruments;
  • Software for analysis of various plate gate valve designs;
  • Tests and analyses of plate-design cut-off fittings for safety and compliance with EU standards.

Partners:

  • Industrial Research Institute for Automation and Measurements PIAP